CONSTRUCTION & PROJECTS
Construction Updates & Latest News
ESTech is always busy with construction projects to bring our members faster services and better connectivity. Information on current construction projects can be found below.
We are currently working on expanding our fiber-to-the-home service in the communities of Kit Carson and Woodrow
Eastern Slope Technologies is on track to complete the USDA Reconnect project this summer with the finalization of the Woodrow phase. For the most current updates on our active and future projects, please check this page regularly.

Rural Eads Fiber – March 2026
Construction Update Custom fiber installs began the week of March 16, 2026. Members have been contacted for scheduling. Custom Fiber install appointments are scheduled for

Kit Carson Fiber – March 2026
Construction Update Custom fiber installs began the week of March 16, 2026. We have begun contacting each member to get them on the schedule for

Rural Eads Fiber – February 2026
Construction Update Mainline construction is complete in rural Eads. Fiber drops have been placed to homes and businesses. Fiber splicing is complete, with testing results

Kit Carson Fiber – February 2026
Construction Update Mainline construction is complete in both rural and the town of Kit Carson. Fiber drops have been placed to homes and businesses. Fiber

Kit Carson Fiber – November 2025
Construction Update Mainline construction is now complete in both rural areas and within the town of Kit Carson. Fiber drops to homes and businesses are

Rural Eads Fiber – November 2025
Construction Update All Fiber Splicing is complete. Custom Fiber Installs to begin December 2025/January 2026. Custom Fiber install appointments are scheduled for a two hour