Construction

Kiowa County Fairgrounds Building

Construction Update Custom fiber installs began the week of March 16, 2026. Members have been contacted for scheduling. Custom Fiber install appointments are scheduled for a two-hour window. While some installations may be completed in less time, others could take slightly longer, depending on your home. If you do not have Eastern Slope Technology services […]

Rural Eads Fiber – March 2026 Read More »

Construction Update Custom fiber installs began the week of March 16, 2026. We have begun contacting each member to get them on the schedule for custom installs. Custom Fiber install appointments are scheduled for a two-hour window. While some installations may be completed in less time, others could take slightly longer, depending on your home.

Kit Carson Fiber – March 2026 Read More »

Kiowa County Fairgrounds Building

Construction Update Mainline construction is complete in rural Eads. Fiber drops have been placed to homes and businesses.  Fiber splicing is complete, with testing results back and ready to go. Custom Fiber installs are scheduled to begin in early March.  Custom Fiber install appointments are scheduled for a two-hour window. While some installations may be completed

Rural Eads Fiber – February 2026 Read More »

Construction Update Mainline construction is complete in both rural and the town of Kit Carson. Fiber drops have been placed to homes and businesses.  Fiber splicing is complete and testing will finish up next week.  Custom Fiber installs are scheduled to begin in early spring.  Custom Fiber install appointments are scheduled for a two-hour window. While

Kit Carson Fiber – February 2026 Read More »

Construction Update Mainline construction is now complete in both rural areas and within the town of Kit Carson. Fiber drops to homes and businesses are finished in rural Kit Carson. Work in town is on track to be completed by the end of November 2025. Fiber splicing will begin once all fiber has been placed.

Kit Carson Fiber – November 2025 Read More »

Kiowa County Fairgrounds Building

Construction Update All Fiber Splicing is complete. Custom Fiber Installs to begin December 2025/January 2026. Custom Fiber install appointments are scheduled for a two hour window. While some installations may be completed in less time, others could take slightly longer, depending on your home. If you do not have Eastern Slope Technology services and are

Rural Eads Fiber – November 2025 Read More »

Fiber to the Home in Haswell Construction information

Construction Update All fiber installs have been completed with a few exceptions.  If you do not have Eastern Slope Technology services and are interested, please contact the Business Office 719-743-2441.  

Haswell Fiber – November 2025 Read More »

Kiowa County Fairgrounds Building

Construction Update Mainline Fiber  and Fiber drops to homes and businesses have been placed. Fiber Splicing began the week of September 22. Custom Fiber installs will begin after fiber splicing and testing are complete. Custom Fiber install appointments are scheduled for a two hour window. While some installations may be completed in less time, others

Rural Eads Fiber – October 2025 Read More »

Construction Update Mainline fiber will be placed Amerine Construction is the construction company Eastern Slope Technologies has contracted to do all the placing of the fiber lines. They are finishing up placing the mainline fiber in rural Kit Carson and will begin placing the mainline in town beginning early this fall. Every residence will receive

Kit Carson Fiber – September 2025 Read More »

Fiber to the Home in Karval Construction Information

Construction Update Karval residents are invited a FREE Community BBQ sponsored by Eastern Slope Technologies! When: Friday, October 10 @ 11 AM to 1 PM Where: Karval Park Why: To celebrate the completion of our Fiber to the Home project Hamburgers and hot dogs Custom Fiber Installs are almost complete. We have called all members

Karval Community BBQ – August 2025 Read More »